Net metering approvals take 6-10 months — the paperwork is the real bottleneck to rooftop solar
highCleanTech AI 79/100 Seeking team

Net metering approvals take 6-10 months — the paperwork is the real bottleneck to rooftop solar

Ahmed Nawaz
Ahmed Nawaz
@ahmednawaz · Posted Oct 8, 2025

I have installed over 400 solar systems in Faisalabad and the single biggest complaint from customers is not the price — it is the wait. A net metering license involves the DISCO, an inspection, a meter change, and file movement between desks that can take anywhere from 6 to 10 months. Customers pay for a system in March and start exporting units in December. Meanwhile the file status is a mystery; people literally pay agents just to find out where their application is sitting. A tracking and documentation service that prepares flawless applications and follows them through FESCO/LESCO would cut approval time in half. The demand is enormous and completely unserved. I know the process inside out and am happy to advise anyone who wants to build this.

#net-metering#solar#bureaucracy#renewable-energy
2 Solutions 982 Views Est. 40,000+ pending net metering applications nationally
AI Analysis Generated 4 hrs ago · Claude Sonnet 4.5

A high-conviction problem with strong founder-market fit signals. The combination of severe price asymmetry, accessible demographics, and existing infrastructure makes this buildable within 9 months by a small team.

TAM
Est. 40,000+ pending net metering applications nationally
Urgency
high
Confidence
High
Time to MVP
9 mo
Impact Score79/100

Solutions · 2

new_idea 74% feasible

A net-metering application tracker that files, follows up, and escalates — TurboTax for DISCOs

Build a service where the installer or customer uploads documents once; the platform generates a complete, error-free application package (most delays start with objections over trivial defects), submits it, then tracks every stage with the DISCO through runners who physically visit offices weekly. Customers see a live status bar instead of a black hole. Charge PKR 15-20k flat — installers would bundle it into every quote. Start with LESCO and FESCO where volumes are highest.

UUsama Nadeem
new_idea 62% feasible

Publish a public dashboard of approval times per DISCO office — sunlight speeds up queues

Crowdsource application dates and approval dates from solar groups (thousands of members share this constantly). Publish average processing time per sub-division office, updated monthly, with the slowest offices named. NEPRA has processing-time rules nobody enforces; a public scoreboard gives journalists and energy ministry people a stick. Costs almost nothing to run and pairs well with any filing service.

MMustafa Jamil

Discussion

Y
B
Basit Majeed10/9/2025

Confirmed from the installer side. I tell customers 8 months honestly and lose the sale to whoever promises 2. The liars are setting market expectations.

M
Mustafa Jamil10/11/2025

Our building's commercial connection application is at month 9. The file has been 'with the SE office' since March. Nobody can tell us what that means.

N
Noman Ashfaq10/14/2025

The factory version of this took us 14 months. We ran diesel gensets the whole time on power we had already bought panels for. The economic waste is national-scale.